Blasting Permits & Regulations

Herriman City regulates blasting operations associated with mining, quarrying, grading, excavation, and land development to help protect the safety of residents, property owners, and the community.

Under Herriman City Code Chapter 4-8, blasting operators must meet specific permitting, notification, monitoring, and safety requirements before conducting blasting activities within City limits. These regulations supplement the operational blasting requirements administered by the Unified Fire Authority.

Whether you live near a proposed blasting site or are preparing to conduct blasting operations, the information below provides an overview of the City's regulations, resident protections, and permit requirements.

Blasting Rules at a Glance

Herriman City has established restrictions on when and where blasting may occur, along with permitting requirements intended to protect public safety. Here are some of the key regulations.

8 AM–5 PM

Permitted Blasting Hours

Blasting operations are permitted Monday through Friday between 8:00 a.m. and 5:00 p.m., unless the City grants a written exception under the ordinance.

City Code 4-8-3(A)
Weekdays Only

Weekend & Holiday Restrictions

Blasting is prohibited on Saturdays, Sundays, and federal or Utah state holidays unless the City grants a written exception based on extraordinary circumstances and adequate public safety measures.

City Code 4-8-3(A)
250 Feet

Occupied Structure Restriction

Blasting is prohibited within 250 feet of an occupied structure unless the City grants a written exception after determining that the proposed blast meets applicable vibration, airblast, and safety requirements.

City Code 4-8-3(B)
2 Permits

Required Before Blasting

Operators must obtain both a Herriman City Blasting Permit and a Unified Fire Authority Operational Blasting Permit before conducting blasting operations within City limits.

City Code 4-8-5 & 4-8-6

Important: These are general requirements. Written exceptions may be granted under specific circumstances outlined in the ordinance. All blasting operations must comply with applicable permit conditions and safety regulations.

Information for Nearby Residents

Herriman City's blasting regulations require advance notification, property survey opportunities, and warning signals for nearby residents.

¼ Mile

Advance Notification

Residents and property owners within ¼ mile (1,320 feet) of a blasting site must receive written notice:

  • 10 calendar days before the first blast if mailed.
  • 7 calendar days before the first blast if hand-delivered.

Notices include the blasting location and schedule, operator contact information, and details about available property surveys.

City Code 4-8-8
600 Feet

Pre-Blast Property Surveys

Owners of structures within 600 feet of a blasting site must be offered a free pre-blast survey.

An independent qualified professional documents existing property conditions through photographs and a written report. The property owner receives a copy.

Declining a survey does not waive a property owner's right to seek compensation for blasting-related damage.

City Code 4-8-9
3 Minutes

Warning Before Blasting

Operators must sound an audible warning, such as a horn or siren, at least three minutes before each blast.

The advance notification must explain the warning signal pattern so nearby residents know what to expect.

City Code 4-8-8

Blasting Permit Requirements

Blasting operators must obtain both permits below before beginning operations within Herriman City.

01

Herriman City Blasting Permit

Required for each blasting project. Permits for ongoing operations may cover a defined area and time period.

02

UFA Operational Blasting Permit

Required from Unified Fire Authority for blasting activities involving explosives.

City Blasting Permit Application Checklist

A complete application must include:

  • Operator information: Name and contact information for the operator.
  • Certified Blaster: Contact information and current certification credentials.
  • Site map: Proposed blast area, structures within 600 feet, public roads within 500 feet, and utilities within 300 feet.
  • Blasting schedule: Anticipated dates, days, and hours of operations.
  • Blast Design Plan: Proposed blasting methods and safety measures.
  • UFA permit: A copy of the UFA Operational Blasting Permit or qualifying written confirmation from UFA.
  • Resident notification and survey plans: Plans for required notifications and pre-blast surveys.
  • Utility protection plan: Notification and coordination with affected utilities.
  • Traffic control: Road closure and traffic control information, when applicable.
  • Additional documentation: Any other information reasonably required by the City.

Application Fee: A nonrefundable fee is required according to Herriman City's adopted fee schedule. A City permit application may be submitted with qualifying UFA confirmation, but blasting cannot begin until the UFA permit is issued.

Application & Approval Process

Herriman City reviews blasting permit applications for compliance with applicable requirements before issuing a decision.

1

Submit Application

Submit the completed City blasting permit application, supporting documentation, and required fee.

2

City Review

The City has 15 business days to review a complete application. A written notice may extend the review by up to 10 additional business days.

3

Permit Decision

The City may approve, approve with conditions, or deny the application. Blasting may begin only after all required permits are issued and applicable conditions are met.

Permit Conditions, Enforcement & Appeals
  • Permit conditions: The City may impose additional requirements to protect public safety, property, and infrastructure.
  • Suspension or revocation: A permit may be suspended or revoked for violations of the ordinance or permit conditions.
  • Appeals: An operator may appeal a permit decision to the City Council within 15 calendar days. A hearing must be held within 30 calendar days as provided by the ordinance.
City Code 4-8-7 and 4-8-13

Blasting Safety & Operational Requirements

Blasting operators must follow additional safety, monitoring, and operational requirements established by Herriman City Code Chapter 4-8.

Ground Vibration & Airblast Limits

Blasting operations must remain within the following maximum ground vibration limits, measured at the nearest occupied structure.

Distance from Blast Maximum Peak Particle Velocity
0–300 feet 0.75 inches/second
301–500 feet 1.00 inches/second
501–1,000 feet 1.25 inches/second
More than 1,000 feet 2.00 inches/second
  • Airblast overpressure may not exceed 133 decibels (Linear).
  • A seismograph must monitor every blast. Monitoring records must be retained for at least three years.
  • Seismograph records must be submitted to the City within five business days after each blast.
  • If a vibration or airblast limit is exceeded, the operator must notify the City in writing within 24 hours and immediately suspend blasting until the City approves a revised plan.
City Code 4-8-3 and 4-8-4
Certified Blasters & General Safety
  • A Certified Blaster must be physically present and directly supervise all explosive loading and firing operations.
  • All blasting must follow an approved Blast Design Plan.
  • Operators must prevent flyrock from leaving the designated blast exclusion zone.
  • Blasting is prohibited during electrical storms or when lightning is detected within five miles of the blasting site.
City Code 4-8-3
Utility Protection Requirements
  • Operators must notify utility providers with facilities located within 300 feet of the blast site.
  • Blue Stakes must be contacted at least 48 hours before excavation, excluding weekends and holidays.
  • Underground utilities must be located and marked before blasting operations.
  • Operators must coordinate with affected utility providers and implement required protective measures.
City Code 4-8-10
Blasting Near Public Roads

Additional safety and traffic control requirements apply when blasting occurs within 500 feet of an operating public road.

  • Road closures may be required to maintain a blast exclusion zone of at least 300 feet.
  • Operators must obtain applicable traffic control permits and provide required advance notifications.
  • Approved traffic control measures, including flaggers when required, must be in place during operations.
  • Operators must coordinate with emergency services and complete required post-blast roadway inspections.
  • Operators are responsible for repairing damage to public roads caused by blasting operations.
City Code 4-8-11

These requirements are a summary of the ordinance. Operators are responsible for complying with all applicable City, state, and federal regulations.

Full Ordinance & Resources

Review the complete ordinance and access additional resources related to blasting operations in Herriman City.

Questions About Blasting Regulations?

For questions about Herriman City's blasting ordinance or permitting requirements, contact Herriman City.